| 
   
  ANOTHER DAM ON THE SHARAVATHI 
  - NGOs-MOEF Ensure 
  Observance Of Guidelines 
  
  Gudakesh 
  
  
  Jog Falls : The mist plays hide 
  and seek with the members of the expert team of the Ministry of Environment & 
  Forests (MOEF) observing the famed falls which have four distinct ones locally 
  named Raja, Roarer, Rocket, Rani, each according to its distinct 
  characteristic.  On occasion they can see the Raja without his crown, or the 
  Rani with her long flowing tresses, then all is lost to the mist; suddenly it 
  lifts and the four falls can be beheld in their glory.  Much of it vanishes 
  once the flow from the dam (at Linganamakki) upstream of the Sharavathi is 
  reduced, for then the falls become a trickle.  The Linganamakki project was 
  completed in the sixties for the purpose of providing power to the state’s 
  industries. 
   
  Another dam is under construction downstream of the falls, at the tail end of 
  the other dams, just before the Sharavathi enters the Arabian sea, hence its 
  name, the Sharavathi Tailrace Project also known as the Gerusoppa project 
  (located at Gerusoppa village, Honnavar taluka, Uttara Kannada district, 
  Karnataka).  The MOEF team is here to examine whether the conditions 
  stipulated by the ministry are being observed so that the forests and its 
  endemic species are not lost to the Tailrace dam, or the wildlife in the 
  region harmed. 
   
  The Tailrace is the third dam for generating power that the Karnataka Power 
  Corporation (KPC) is constructing with the concomitant power station.  The 
  other two dams on the Sharavathi are at Linganamakki and Talakalale,  The 
  three power houses are the Linganamakki (two units of 55 MW each), the 
  Sharavathi station (890 MW, the largest in Asia) and the one near the Tailrace 
  dam (4 units of 60 MW).  
   
  The Sharavathi Tailrace Project was given the green signal (“conditional  
  environmental clearance”) by the MOEF on March 25, 1987 subject to the KPC 
  observing eight safeguards noted in its letter.  The clearance was revoked on 
  July  31, 1992 because its stipulations were not being observed by the 
  corporation.  A year and two months later the MOEF re-issued the clearance was 
  revoked on July 31 1992 because its stipulations were not being observed by 
  the corporation.  A year and two months later the MOEF re-issued the clearance 
  while imposing 12 safeguards in addition to the eight listed by it on March 
  25, 1987. 
   
  The team visited the dam site at Gerusoppa where it invited local NGOs for 
  discussion to obtain their perspective on the Tailrace project and the details 
  on the implementation of the safeguards by the KPC. 
   
  Some of the safeguards (guidelines) maybe listed: 
  
   
  1. 
  The land capability and vulnerability survey in the catchment of the 
  Sharavathi Tailrace Projects should be carried out to delineate critically 
  degraded areas needing priority treatment.  The amount of Rs. 10 lakhs 
  presently earmarked for the soil conservation work should be accordingly 
  enhanced depending on the nature of work and area to be covered. 
  2. 
  Even 
  though no population is going to be effected due to the submergence created by 
  the project, since sizeable forest  area is required  to be diverted, measures 
  should be initiated to ensure nistar rights of local people. 
  3. 
  Detailed survey on aquatic flora 
  and fauna should be carried out to ascertain existence of species like 
  Mahaseer with plans for their salvation. 
  4. 
  Migratory corridors of elephants 
  should be delineated in consultation with the Chief Wildlife Warden, Karnataka 
  and vegetation cover in the area  should accordingly be enhanced in the 
  project impact zone. 
  5. 
  Since 10 lift 
  irrigation schemes providing irrigation to about 750 ha are presently under 
  operation in the downstream stretch of the project, sufficient control 
  measures should be built into the project operations to ensure that adequate 
  water is released even in the lean season. 
   
  
  The Tailrace project was contemplated as far 
  back as the mid-sixties.  The dam height will be 58 metres across the 
  Sharavanthi near Gerusoppa village and the power house will be located “at the 
  toe of the dam”.  The dam will impound water to a full reservoir level 
  submerging 596 hectares of forest land in the valley.  In total 700 hectares 
  of forests will be lost, a little more than a 100 being taken up by roads, 
  houses, quarries. 
   
  The forests in the Sharavathi catchment area are evergreen or semi-evergreen 
  type.  The Economics Agriculture and Ecology Consortium (EAEC) study points 
  out that “the project area is covered by southern tropical evergreen forests.  
  Several biotic factors have considerably reduced the density of these forests 
  over centuries.  The partially closed forests canopy is made up of the 
  confluent crowns of medium size trees.  The dense canopy ensures controlled 
  conditions of light and degree of humidity within the forest.  The banks of 
  the Sharavathi abounds in plants that are specially tolerant to water-logging 
  and yield leaves, flower and fruit during the late winter season.”  Besides, 
  treeless, shrubs are found.  “The ground cover”, the study adds “has a rich 
  composition  of mesic plants especially during the monsoon months.  Mosses are 
  aplenty, as well as lichens and fungi.  The role of fungi in breaking down the 
  forest debris into simple  organic nutrients in the natural process of 
  recycling is well known.” 
   
  A migratory path near Ambepalgudda has been observed; elephants often use it.  
  The storage of water (in the dam) will restrict their movement within the left 
  bank which has a vast stretch of forest without human habitation.  Wild 
  animals are scarce on the right bank, perhaps because of human habitation 
  along the Bangalore-Honnavar road whereas on the left bank the animals  are 
  more secure and live under protective cover of the forest. 
   
  Apart from elephants, the other fauna available in the project area include 
  tiger, panther, langurs, gaur as well  as bears and mouse deer.  The rare 
  species found here is the lion-tailed monkey, declared endangered all over the 
  world.  There is a larger population of prey animals than predators. 
   
  Among the avian species are the grey jungle fowl, Indian great hornbill, 
  Malabar pied hornbill, Keel, Hoopi, Brahimini kite. 
   
  The studies indicate that there are 34 varieties of fresh water fish, 
  including the Mahaseet and 27 varieties of entuarine fish  species re Tor 
  Kudree, Tor Musullah, Tor Neilli, Angula species and Labeo callbasu.  We are 
  told that in southern Indian rivers where “abundant economic variety fauna are 
  found”. 
   
  The Tailrace project is under attach for the threat it poses to the above 
  mentioned flora and fauna --- and more.  Almost everywhere dams, in particular 
  large ones, have been criticised for not being cost-effective, and for the 
  rehabilitation/ dislocation and environment costs they incur.  So far about 58 
  large, 152 medium, 2155 small reservoirs (total 2365) have been built in 
  different river basins of India which together have a water spread area of 3 
  million hectares at the full reservoir level (FRL).  India accounts for more 
  than 50 percent of the total reservoir area in south-east Asia. 
   
  Undeniably the most controversial in recent times has been the Narmada 
  (Gujarat, Madhya Pradesh and Maharashtra) largely because of the failure on 
  the part of the authorities to re-habilitate the tribals; they have been 
  shunted off to areas alien to their environment; and even the forest area 
  where they have been re-settled (as in Maharashtra) has generated controversy 
  because it has involved the destruction of green cover. In several cases, the 
  tribals refused to move from their villages, being prepared to drown under the 
  impounded waters. In the case of Tehri dam (Garhwal) the people have not 
  shifted even after receiving compensation; Tehri town continues to be occupied 
  and several residents have even rented their homes. Unlike the Namada oustees, 
  the residents of Tehri and nearby villages do not fear going under because 
  once the Soviet Union collapsed, the funds for the project dried up.  The 
  authorities are looking around for resources to  continue work on it. 
   
  Rehabilitation with regard to the Pooyamkutty dam (Kerala), however, has not 
  posed a problem because the number of people involved has been limited; in the 
  case of the Tailrace no rehabilitation is required.  The pooyamkutty project 
  area has among the richest forests and vegetation this write has come across, 
  as has been documented in these columns earlier.  Like Pooyamkutty, the 
  Tailrace project too is in the Western Ghats and the vegetation is similar, 
  the potential loss of which has agitated environmental groups in the region. 
   
  In fact, they took the matter to the Karnataka high court and at one stage two 
  cases were pending before it.  The MOFF clearance was revoked as a result of 
  the high court order of January 1991 with reference to the court petition No 
  8170 filed in 1988 by the Sharavathi Tailrace Yojana Horata Samiti and the 
  Honnavar Taluka Parisara Koota. 
   
  The NGOs cite the report of the deputy conservator of forests, Hunnavar (Prabhu) 
  who opposed submersion in 1985 observing that the forest’s “micro environment 
  will be damaged”.  Others too have opposed the project.  The report of Dr. 
  Subhaschandran of the loss of the “richness and biodiversity of the valley”.  
  The 1990 report of Dr. K.M. Safeeulla, the then vice chancellor of Mangalore 
  university, demanded that the project be halted to save the Sharavathi valley. 
   
  The studies have identified several new species of plants and fungi that would 
  be endangered by the project.  One study noted that among the six endangered 
  species of Mahaseer, four were to be found in the Tailrace project area.  The 
  project would pose a threat to other rare species like the King Cobra, lion- 
  tailed macaques (for whose preservation the Silent Valley Project was halted) 
  and the migratory path of elephants would be disturbed. 
   
  The NGOs, who base their criticism on the above reports as well as they study 
  of the Central Water Commission in 1973 and the project report  of 1981, point 
  to the technical defects of the dam.  The geological one is that the KPC, 
  which initially began in the construction of the powerhouse on the left bank 
  of Sharavathi, shifted it to the right bank, because of the geological faults, 
  “but now the powerhouse will be occupying the same site as the embankment line 
  on the right bank which was shifted 150 metres upstream’. 
   
  Initial studies indicated heavy seepage along the periphery.  Though KPC has 
  taken into account the loss as a result of evaporation, it has not done so 
  with regard to seepage.  Moreover, the water inflow for the Tailrace project 
  is calculated upto 1980.  But since it has reduced each successive year, this 
  is a major lapse on the part of KPC. 
   
  Apart from the environmental and technical objections, the NGOs led by Ganesh 
  Bhat of the Sharavathi Tailrace Yojana Horata Samiti and Anant Hegde of Save 
  Western Ghats Movement,  have several on socio-economic grounds as well.  They 
  observe that the downstream effects of the project have not been given 
  sufficient attention: (I) the Sharavathi river joins the Arabian Sea no more 
  than 32 km from the dam site.  The salt-water effect is upto five kilometres 
  from the sea; if this “band” shifts further upstream and the river water turns 
  brackish, thousands of farmers who use the river, will suffer; (ii) the nistar 
  rights of the people of the region has/will be affected as also (iii) the 
  fuelwood supply of the local population. 
   
  Then there is the manner in which the project is being implemented.  At the 
  quarry in the forest some distance from the dam site from where material 
  (rock, stone, rubble) for the dam construction is collected, the blasting 
  operations are producing vibrations, gases, dust and sound which are affecting 
  the fauna of the region, so much so that Dr. Kusuma, President of Honnavar 
  Taluka Parisar Koota said she had to treat victims of animal attacks living 
  around the dam site. 
   
  The labour force of 500 people is expected to be supplied fuelwood by the 
  contractor (Mr. Sundar) from outside the forest area.  But there is no way of 
  checking that the labour does not on the quiet secure some of its fuelwood 
  requirements from the forests, as also indulge in poaching. 
   
  The compensatory afforestation/catchment area treatment by the KPC has to be 
  done as per the (I) Forest Conservation Act and (ii)  the Environment 
  Protection Act.  In accordance with the Forest Act, the survival rate of 
  saplings on parts of the 680 hectares that have been examined by the forest 
  department, is as high as 90 percent.  However, the KPC has so far not even 
  submitted its plans to undertake catchment area treatment of 700 hectares as 
  per the Environment Act. 
   
  The KPC’s response to some of the major allegations  is as follows: 
  The plants termed as endemic to the Tailrace project area are not endemic to 
  it.  They have wide distribution throughout the Western Ghats.  Regarding 
  nistar rights, it has been observed that locals collect green and  dried 
  leaves for manure, as well as bamboo and reeds.  But they have no other  
  rights over the forest as it is a reserved forest. 
   
  The upstream of the Sharavathi river (below jog falls) is a deep cut valley 
  with fairly steep slope in a mountainous terrain and as such the chances of 
  seepage are very remote in the vicinity.  The water loss tests conducted “in 
  the overburden at FRL (full reservoir level) indicate that the seepage losses 
  are negligible.” 
   
  The downstream of the proposed dam site is a coastal plain with small 
  agricultural fields growing paddy; areca and coconut are cultivated by lift 
  irrigation.  The utilisation of water for lift irrigation is very meagre 
  compared to the quantity of water flowing in the river during different months 
  of the year. 
   
  Before the construction of the dams on Sharavathi, the river used to be active 
  during the monsoon and almost dry during summer.  The tidal water would extend 
  up to Gerusoppa village making the water saline after the monsoon.  After 
  impoundment at Linganamakki and Talakalale and the consequent constant flow in 
  the river, the impact of tidal water has been pushed beyond Hosadi village.  
  On completion of the Tailrace project, the flow will not decrease, rather it 
  will increase and hence there is no possibility of inpushing of saline water. 
   
  As long as the thrust and parry process between the NGOs and the KPC continue, 
  there is a good chance of the MOEF guidelines being implemented.  But their 
  implementation is dependent on the multi-disciplinary high-power committee 
  that has been set up (as per the guidelines).   However, it has met only 
  once.  In the circumstance, the project implementor (the KPC) is burdened with 
  the responsibility of also enforcing the guidelines, a rather unrealistic 
  situation in terms of (a) impartiality and (b)  availability of expertise.  
  Both these are essential for the protection/preservation of the Sharavathi 
  Valley’s flora and fauna, a job that only the high power committee can do.  
  Why is the Karnataka government preventing it from doing its job? 
  
    
    
      
        
        
        Extract from Monoo Nalapat’s interview 
        with Maneka Gandhi, the then minister of state for environment and 
        forests, published in The Times of India of August 14, 1990.  Ms. Gandhi 
        stated : 
         
        “Or take a second example of a scam in the name of ‘development’ the 
        so-called ‘Tail Race dam’ in Sharavathi in Karnataka.  We were told that 
        yes, thousands of acres would be submerged but that this was all 
        ‘barren’ land.  A bureaucrat from the Centre went down to Karnataka and 
        reported, after checking the site, that the land was indeed ‘totally 
        barren’. 
         
        ‘Then I started getting complaints of animals attacking humans, animals 
        that had been driven to human habitats by the cutting down of their 
        forests.  How could there beforests in a ‘barren’ area?  I sent an 
        officer - an honest one this time - to investigate, and he told me that 
        the land (to be submerged) was in fact a thick rain forest.  Each tree 
        that is cut would be worth several thousand rupees, and they would all 
        be stolen be the contractor, as the land is on paper supposed to be 
        ‘barren’. 
         
        “The proposed dam would destroy two to three thousand hectares of 
        forest, and in return electrify and irrigate only a few villages.  But 
        officials, contractors and their political henchmen would rake in crores, 
        which is why the project is being demanded.” | 
       
     
    
   
  
  Back to Contents 
    
  
      
      |